Supply and Install Timelines

4Kitchens cater to the skill, time and experience of all our clients. Whether you want us to provide a full installation service, pre-assembled units that are easy to fit, or you want to do it all yourself in flatpack form we will happily cater to your needs.

We have implemented a Quality Assurance system to ensure that your job is completed in full and on time, every time to your satisfaction.

Download Our Design and Install Timeline

 

DESIGN TIMELINE:

 

  1. Contact us for a FREE design consultation
  2. Review the design and material selection
  3. Detailed proposal of costing presented
  4. Sign off on proposal and 50% deposit payment
  5. Formal site measure within 48 hours
  6. Final working drawings presented for approval
  7. 3 weeks later start installation process

 WHAT TO EXPECT DURING INSTALLATION

 

DAY: 1

Disconnect – plumbing, gas and electrics to make work safe.

Removal of old cabinets and splashbacks.

*If no other structural work is required

**If you need to retile or move power points and/or plumbing this happens prior to the install of the new cabinets.

DAY: 2

Install new cabinets.

DAY: 3

Afternoon of the third day the benchtop is measured by stone mason – Allow 5 working days for stone preparation

 

 

 

DAY: 8

Benchtop is installed.

DAY: 9

Tile splashback is installed.

*If glass splashback is chosen, this is measured once the benchtop is installed. Allow 3 weeks, however the kitchen can be used in this time.

**If a stone splashback is chosen, allow 5 working days.

DAY: 10

Fit off final plumbing and electrical items.

Kitchen is complete – Enjoy your kitchen for years to come!

Disclaimer: This is a typical timeline. Each client is treated on an individual basis and may require other works to be completed or the works may be completed in a shorter timeframe. We develop a timeline with you based on your specific needs.